1341 N BENTON WAY 90026
Certificate Information: 1341 N BENTON WAY 90026
- Application / Permit
- 22047-30000-00339
- Plan Check / Job No.
- B22WL00693
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool per standard plan #100 *** 1 of 2 ***
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Current Status
- CofO Issued on 6/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | EDWIN ESPIN |
| Corrections Issued | 2/18/2022 | EDWIN ESPIN |
| Plan Check Approved | 6/27/2022 | EDWIN ESPIN |
| Issued | 8/10/2022 | APPLICANT |
| Building Plans Picked Up | 8/12/2022 | APPLICANT |
| CofO in Progress | 5/26/2023 | THOMAS LOGRASSO |
| Permit Finaled | 6/3/2023 | DEROLD HAUFF |
| CofO Issued | 6/3/2023 | DEROLD HAUFF |
| Permit Finaled | 6/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/27/2022 | EDWIN ESPIN |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Gunite | 12/14/2022 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Gunite | 12/19/2022 | Approved | THOMAS LOGRASSO |
| Grounding or Bonding | 3/31/2023 | Approved | THOMAS LOGRASSO |
| Enclosure/Fence | 4/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Enclosure/Fence | 4/18/2023 | Approved | JEFFREY MEAD |
| Pool Equipment Noise Test | 5/11/2023 | Corrections Issued | JUAN ESCOTO DELGADO |
| Pool Equipment Noise Test | 5/16/2023 | Approved | ZEYDI STEWART |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Approved | THOMAS LOGRASSO |
| Final | 5/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Final | 5/26/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/26/2023 | SGSOV Approved | THOMAS LOGRASSO |