518 E SUNSET AVE 90291
Certificate Information: 518 E SUNSET AVE 90291
- Application / Permit
- 22047-30000-00333
- Plan Check / Job No.
- B22WL00676
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New Pool/ Spa
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | MARJAN SHENASI |
| Corrections Issued | 2/20/2022 | MARJAN SHENASI |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
| Applicant returned to address corrections | 4/14/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 6/29/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/15/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 11/21/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/9/2022 | DANIEL SMILEY |
| Plan Check Approved | 12/21/2022 | AMY GUEVARRA |
| Issued | 12/21/2022 | APPLICANT |
| CofO in Progress | 2/6/2025 | DAVID FEILER |
| CofO Issued | 2/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/16/2022 | MAYELA VILLA |
| Miscellaneous | Cleared | 3/16/2022 | MAYELA VILLA |
| ZA Case | Cleared | 3/16/2022 | MAYELA VILLA |
| ZA Case | Cleared | 3/16/2022 | MAYELA VILLA |
| Coastal Zone | Cleared | 6/16/2022 | NOAH MCCOY |
Contact Information
| Contractor | Morales Pools; Lic. No.: 901495-C53 | 1020 ELECTRIC AVENUE VENICE, CA 90291 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/1/2023 | Corrections Issued | EVAN COOPER |
| Deputy Shotcrete | 6/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Deck | 9/15/2023 | Approved | HERBERT GIRON |
| Enclosure/Fence | 10/18/2024 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 10/22/2024 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 10/24/2024 | Approved | HERBERT GIRON |
| Grounding or Bonding | 10/24/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 1/23/2025 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 1/23/2025 | Approved | MICHAEL ALLEN |
| Final | 1/23/2025 | OK to Issue CofO | MICHAEL ALLEN |
| PLUMBING-Final | 1/23/2025 | Approved | MICHAEL ALLEN |
| Pre-Gunite | 1/23/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | MICHAEL ALLEN |