2621 N HUTTON DR 90210

Certificate Information: 2621 N HUTTON DR 90210

Application / Permit
22047-30000-00168
Plan Check / Job No.
B22WL00330
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
new pool 32'x 15' 3.5' deep to 6' deep with attached spa 6'x 6' per std. plan # 268 *** 1 of 2 ***
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 MANUEL GARCIA
Corrections Issued 2/5/2022 MANUEL GARCIA
Applicant returned to address corrections 3/10/2022 JASON JANGADA
Applicant returned to address corrections 3/23/2022 JASON JANGADA
Building Plans Picked Up 3/24/2022 APPLICANT
Applicant returned to address corrections 4/26/2022 JASON JANGADA
Plan Check Approved 5/7/2022 EDWIN ESPIN
Issued 5/24/2022 APPLICANT
CofO in Progress 5/7/2025 SEAN HAUPT
Permit Finaled 6/3/2025 RICHARD STEINBACH
CofO Issued 6/3/2025 RICHARD STEINBACH
Permit Finaled 6/3/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2022 STEVEN JIN
Watercourse Cleared 2/26/2022 MAHELET GEBEYHU

Contact Information

Contractor Flexi - Tech Contracting Inc; Lic. No.: 767683-B 6924 CANBY AVENUE UNIT 105      RESEDA, CA 91335
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 1/5/2024 Corrections Issued STEPHANIE SWANSON
Deputy Shotcrete 1/9/2024 Conditional Approval MICHAEL PELHAM
Pool Piping 2/27/2024 Approved SEAN HAUPT
Pre-Gunite 2/27/2024 Approved SEAN HAUPT
Rough-Electrical 2/27/2024 Approved SEAN HAUPT
Rough-Plumbing 2/27/2024 Approved SEAN HAUPT
Special/Order Compliance 2/27/2024 Corrections Issued SEAN HAUPT
Grounding or Bonding 3/14/2024 Partial Approval SEAN HAUPT
ELECTRICAL-Final 3/22/2024 Not Ready for Inspection SEAN HAUPT
Gas Piping or Gas Test 3/22/2024 Approved SEAN HAUPT
Rough-Electrical 3/22/2024 Approved SEAN HAUPT
Deck 4/16/2024 Approved SEAN HAUPT
Grounding or Bonding 4/16/2024 Approved SEAN HAUPT
Enclosure/Fence 3/21/2025 Approved DANIEL VERA
Excavation/Setback/Form/Re-Bar 4/7/2025 Not Ready for Inspection DANIEL VERA
Final 4/7/2025 Corrections Issued DANIEL VERA
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Not Ready DANIEL VERA
Excavation/Setback/Form/Re-Bar 4/17/2025 Approved ARAM AVEDISIAN
Final 4/17/2025 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Approved ARAM AVEDISIAN
Final 5/6/2025 OK to Issue CofO SEAN HAUPT