1289 N BEVERLY GROVE PL 90210
Certificate Information: 1289 N BEVERLY GROVE PL 90210
- Application / Permit
- 22047-30000-00098
- Plan Check / Job No.
- B22WL00158
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL & SPA @ UPPER TERRACE LEVEL
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Current Status
- Issued on 1/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | TARIK SAOUD |
| Corrections Issued | 2/14/2022 | TARIK SAOUD |
| Quality Review Completed | 3/4/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 8/31/2022 | TARIK SAOUD |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| Applicant returned to address corrections | 10/13/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 11/14/2022 | REZA HAGHIGHAT |
| Issued | 1/5/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/14/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 11/14/2022 | TARIK SAOUD |
Contact Information
| Architect | , ; Lic. No.: C34639 | 5574 WASHINGTON BLVD LOS ANGELES, CA 90016 |
| Contractor | Hill Pete Construction Company Inc; Lic. No.: 470065-B | 4626 ALBUQUERQUE ST 2ND FLOOR SAN DIEGO, CA 92109 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Engineer | Larocca,, Francis Joseph; Lic. No.: C75121 | 1821 PACIFIC COAST HWY 38 HERMOSA BEACH, CA 90254 |
| Geologist | , ; Lic. No.: GEO2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Geologist | Byrne,, Gregory S.; Lic. No.: EG1933 | 5449 RUTHWOOD DRIVE CALABASAS, CA 91302 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/21/2023 | Partial Approval | BRENDAN LOONEY |
| Pool Piping | 9/7/2023 | Partial Approval | BRENDAN LOONEY |
| Rough-Plumbing | 9/7/2023 | Partial Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 9/13/2023 | Partial Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Partial Approval | BRENDAN LOONEY |
| Pool Piping | 10/24/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Pool Piping | 10/25/2023 | Partial Approval | BRENDAN LOONEY |
| Rough-Plumbing | 10/25/2023 | Partial Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 12/14/2023 | Partial Approval | BRENDAN LOONEY |
| Grounding or Bonding | 12/14/2023 | Partial Approval | BRENDAN LOONEY |
| Pool Piping | 12/14/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Other (see comments) | 12/18/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Other (see comments) | 1/9/2024 | Conditional Approval | MICHAEL PELHAM |
| Pool Piping | 1/11/2024 | Approved | BRENDAN LOONEY |
| Rough-Plumbing | 1/11/2024 | Approved | BRENDAN LOONEY |
| Deputy Other (see comments) | 2/23/2024 | Conditional Approval | BRENDAN LOONEY |
| Deputy Shotcrete | 2/23/2024 | Approved | SEAN HAUPT |
| Deputy Shotcrete | 2/26/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 2/29/2024 | Approved | SEAN HAUPT |
| Pool Piping | 2/29/2024 | Partial Approval | SEAN HAUPT |
| Rough-Electrical | 2/29/2024 | Partial Approval | SEAN HAUPT |
| Rough-Plumbing | 2/29/2024 | Partial Approval | SEAN HAUPT |
| Deputy Shotcrete | 3/1/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Shotcrete | 3/5/2024 | Conditional Approval | MICHAEL PELHAM |
| Pool Piping | 4/8/2024 | Partial Approval | SEAN HAUPT |