10386 W STRATHMORE DR 90024
Certificate Information: 10386 W STRATHMORE DR 90024
- Application / Permit
- 22047-20000-02581
- Plan Check / Job No.
- B22VN19073
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20' X 40' POOL WITH A 7' X 10' SPA PER LA STANDARD PLAN# 268
- Permit Issued
- Issued on 12/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2022 | JESSE ARELLANO |
| Issued | 12/28/2022 | APPLICANT |
| CofO Issued-Status Void | 11/29/2025 | RICHARD STEINBACH |
| Permit Finaled-Status Void | 11/29/2025 | RICHARD STEINBACH |
| Re-Activate Permit | 12/2/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/2/2025 | RICHARD STEINBACH |
| CofO Corrected | 12/2/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/2/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/28/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| Pool Piping | 12/18/2023 | Approved | STEPHANIE SWANSON |
| Pre-Gunite | 12/18/2023 | Approved | STEPHANIE SWANSON |
| Rough-Electrical | 12/18/2023 | Approved | STEPHANIE SWANSON |
| Rough-Plumbing | 12/18/2023 | Approved | STEPHANIE SWANSON |
| Deputy Shotcrete | 12/20/2023 | Conditional Approval | MICHAEL PELHAM |
| Grounding or Bonding | 4/3/2024 | Approved | STEPHANIE SWANSON |
| Enclosure/Fence | 6/18/2025 | Approved | DANIEL VERA |
| Final | 10/30/2025 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Approved | DANIEL VERA |
| Equipment Noise Level | 11/6/2025 | Approved | MIKE WANG |
| Final | 11/7/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 11/21/2025 | Conditional Approval | DANIEL VERA |