441 N ROCKINGHAM AVE 90049
Certificate Information: 441 N ROCKINGHAM AVE 90049
- Application / Permit
- 22047-20000-02482
- Plan Check / Job No.
- B22VN18359
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (48'-4"x32'-0") INFINITY EDGE POOL W/(5'-8"x5'-8") SPA ON PILES AND GRADE BEAMS.
- Permit Issued
- Issued on 5/31/2023
- Issuing Office
- Current Status
- CofO Issued on 5/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | PETER MOSESIAN |
| Corrections Issued | 1/26/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/31/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 2/6/2023 | APPLICANT |
| Plan Check Approved | 5/31/2023 | PETER MOSESIAN |
| Issued | 5/31/2023 | APPLICANT |
| CofO in Progress | 5/5/2025 | ARAM AVEDISIAN |
| Permit Finaled | 5/29/2025 | RICHARD STEINBACH |
| CofO Issued | 5/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 2/9/2023 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 3/21/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Flexi - Tech Contracting Inc; Lic. No.: 767683-B | 6924 CANBY AVENUE UNIT 105 RESEDA, CA 91335 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Danz,, Joshua; Lic. No.: C84764 | 1164 ELDERBERRY CIRCLE FOLSOM, CA 95630 |
| Engineer | Echeverria,, Andres; Lic. No.: C89926 | 18142 ARMINTA ST RESEDA, CA 91335 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/3/2023 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 8/7/2023 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Other (see comments) | 6/11/2024 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Other (see comments) | 6/27/2024 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 6/28/2024 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 6/28/2024 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 6/28/2024 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 7/1/2024 | No Access for Inspection | KENNETH NAGLE |
| Gas Piping or Gas Test | 7/17/2024 | Approved | KEVIN SARGSYAN |
| Grounding or Bonding | 11/15/2024 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 3/21/2025 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 3/27/2025 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 3/28/2025 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 4/2/2025 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 4/16/2025 | Approved | EUSEBIO GUZMAN |
| Final | 5/2/2025 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 5/5/2025 | OK to Issue CofO | ARAM AVEDISIAN |