11350 W CHENAULT ST 90049

Certificate Information: 11350 W CHENAULT ST 90049

Application / Permit
22047-20000-02421
Plan Check / Job No.
B22VN17894
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 20' X 39' SWIMMING POOL WITH 10' X 10' INTERIOR SPA. WORK PER STANDARD PLAN #268.
Permit Issued
Issued on 5/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/6/2022 ROSENDO MEDINA
Plan Check Approved 12/6/2022 ROSENDO MEDINA
Issued 5/11/2023 APPLICANT
CofO in Progress 4/19/2024 CARLOS MATAMOROS
CofO in Progress 4/21/2024 CARLOS MATAMOROS
Permit Finaled 4/23/2024 DANIEL ORRANTE
CofO Issued 4/23/2024 DANIEL ORRANTE
Permit Finaled 4/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 12/6/2022 TINA MIRANDA
Grading Pre-Inspection Cleared 12/6/2022 ROSENDO MEDINA

Contact Information

Contractor Agam Pool And Spa Inc; Lic. No.: 993464-C53 12940 ADDISON STREET      SHERMAN OAKS, CA 91423

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2023 Approved CARLOS MATAMOROS
Gas Piping or Gas Test 9/27/2023 Approved CARLOS MATAMOROS
Grounding or Bonding 9/27/2023 Approved CARLOS MATAMOROS
Pool Piping 9/27/2023 Approved CARLOS MATAMOROS
Pre-Gunite 9/27/2023 Approved CARLOS MATAMOROS
Rough-Electrical 9/27/2023 Approved CARLOS MATAMOROS
Deputy Shotcrete 10/4/2023 Conditional Approval MICHAEL PELHAM
Enclosure/Fence 12/5/2023 Corrections Issued CARLOS MATAMOROS
Enclosure/Fence 12/6/2023 Approved CHRISTOPHER WILSON
Special/Order Compliance 12/6/2023 Corrections Issued CHRISTOPHER WILSON
Pool Equipment Noise Test 3/5/2024 Approved JAMES VORHIS
Final 4/16/2024 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Not Ready CARLOS MATAMOROS
Pre-Inspection 4/17/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 4/18/2024 Approved CARLOS MATAMOROS
Final 4/18/2024 Partial Approval CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved CARLOS MATAMOROS
Final 4/19/2024 OK to Issue CofO CARLOS MATAMOROS