10819 N GRAY FOX CT 91311
Certificate Information: 10819 N GRAY FOX CT 91311
- Application / Permit
- 22047-20000-02398
- Plan Check / Job No.
- B22VN17740
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17'-0" x 51'-8" SWIMMING POOL AND 8'-6" x 8'-11" SPA WITH BAJA PER CITY STD PLAN # 268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 1/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2022 | RAMA DABADGE |
| Corrections Issued | 12/7/2022 | RAMA DABADGE |
| Building Plans Picked Up | 12/9/2022 | APPLICANT |
| Issued | 1/20/2023 | APPLICANT |
| CofO in Progress | 6/13/2024 | DAVID SCANTLIN |
| Permit Finaled | 7/11/2024 | JOHN JANSON |
| CofO Issued | 7/11/2024 | JOHN JANSON |
| Permit Finaled | 7/11/2024 | JOHN JANSON |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| ZI | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Craftscape Creations Llc; Lic. No.: 1050430-C53 | 15030 VENTURA BLVD #574 SHERMAN OAKS, CA 91403 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 5/1/2023 | Approved | DAVID SCANTLIN |
| Pre-Gunite | 5/1/2023 | Approved | DAVID SCANTLIN |
| Rough-Electrical | 5/1/2023 | Approved | DAVID SCANTLIN |
| Rough-Plumbing | 5/1/2023 | Approved | DAVID SCANTLIN |
| Deputy Shotcrete | 5/18/2023 | Conditional Approval | DAVID SCANTLIN |
| Gas Piping or Gas Test | 6/30/2023 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 4/18/2024 | Corrections Issued | DAVID SCANTLIN |
| Enclosure/Fence | 4/25/2024 | Approved | DAVID SCANTLIN |
| Pool Equipment Noise Test | 6/5/2024 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 6/12/2024 | Approved | DAVID SCANTLIN |
| Final | 6/12/2024 | OK to Issue CofO | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | DAVID SCANTLIN |