230 W OLYMPIC BLVD 90015
Certificate Information: 230 W OLYMPIC BLVD 90015
- Application / Permit
- 22047-20000-02352
- Plan Check / Job No.
- B22VN17468
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- NEW 29'-6" X 78' PUBLIC POOL AT LEVEL 6 OF MIXED-USED BUILDING PER STANDARD PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 2/15/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 5/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 11/28/2022 | APPLICANT |
Disabled Access Plans Picked Up | 12/21/2022 | APPLICANT |
Assigned to Plan Check Engineer | 12/22/2022 | RAPHAEL ROSAS |
Corrections Issued | 12/27/2022 | RAPHAEL ROSAS |
Quality Review Completed | 12/28/2022 | STEVEN KIM |
Building Plans Picked Up | 1/11/2023 | APPLICANT |
Plan Check Approved | 2/15/2023 | RAPHAEL ROSAS |
Issued | 2/15/2023 | APPLICANT |
Permit Finaled | 5/5/2025 | NICK DANERI |
Permit Application Clearance Information
Sewer availability | Cleared | 1/9/2023 | CINDY QI |
Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | CINDY QI |
"D" conditions | Cleared | 1/26/2023 | ASHLEY RODARTE |
"Q" conditions | Cleared | 1/26/2023 | ASHLEY RODARTE |
Tract Map conditions | Cleared | 1/26/2023 | ASHLEY RODARTE |
Redevelopment Project Area | Cleared | 1/30/2023 | DAVID URITA |
ZI | Cleared | 1/30/2023 | DAVID URITA |
DAS Clearance | Cleared | 2/8/2023 | OLLIE CARTER |
Public Swimming Pool approval | Cleared | 2/15/2023 | LACDHS APPROVED |
Contact Information
Contractor | Addison Pools Inc; Lic. No.: 753417-B | 4363 WOODMAN AVENUE SHERMAN OAKS, CA 91423 |
Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
METHANE-Rough | 5/1/2024 | Approved | NICK DANERI |
Pre-Gunite | 5/1/2024 | Approved | NICK DANERI |
Deck | 8/14/2024 | Partial Approval | NICK DANERI |
Enclosure/Fence | 3/5/2025 | Partial Approval | NICK DANERI |
Excavation/Setback/Form/Re-Bar | 5/5/2025 | Approved | NICK DANERI |
Final | 5/5/2025 | Permit Finaled | NICK DANERI |
METHANE-Barrier | 5/5/2025 | Approved | NICK DANERI |
METHANE-Subgrade | 5/5/2025 | Approved | NICK DANERI |
SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Approved | NICK DANERI |