333 N ALFRED ST 90048
Certificate Information: 333 N ALFRED ST 90048
- Application / Permit
- 22047-20000-02320
- Plan Check / Job No.
- B22VN17169
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 11' X 32' POOL WITH A 7' X 11' SPA - ALL WORK PER LA CITY STANDARD PLAN 268 AND SUPPLEMENTAL DETAIL 271
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 11/18/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 11/21/2022 | JOSEPH RAFOLS |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 12/19/2023 | LILIANA PORTILLO |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/16/2022 | Approved | MICHAEL LEWIS |
| Pool Piping | 12/16/2022 | Approved | MICHAEL LEWIS |
| Pre-Gunite | 12/16/2022 | Approved | MICHAEL LEWIS |
| Deputy Shotcrete | 12/21/2022 | Conditional Approval | MICHAEL LEWIS |
| Enclosure/Fence | 6/9/2023 | Corrections Issued | LILIANA PORTILLO |
| Grounding or Bonding | 6/9/2023 | Corrections Issued | LILIANA PORTILLO |
| Enclosure/Fence | 6/15/2023 | Conditional Approval | LILIANA PORTILLO |
| Grounding or Bonding | 6/15/2023 | Approved | LILIANA PORTILLO |
| Pool Equipment Noise Test | 7/7/2023 | Not Ready for Inspection | ANDEY CHAPARRO |
| Equipment Noise Level | 7/11/2023 | Not Ready for Inspection | ANDEY CHAPARRO |
| Equipment Noise Level | 7/18/2023 | Approved | ANDEY CHAPARRO |
| Final | 7/24/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/24/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 12/18/2023 | OK to Issue CofO | LILIANA PORTILLO |