8068 W FAREHOLM DR 90046
Certificate Information: 8068 W FAREHOLM DR 90046
- Application / Permit
- 22047-20000-02282
- Plan Check / Job No.
- B22VN16870
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14'-0" x 13'-9" SWIMMING POOL WITH ATTCHED 8'-4" x 13'-9" SPA PER CITY STD PLAN #268 WITH ENGINEERING DETAILS
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 11/15/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/16/2022 | APPLICANT |
| Applicant returned to address corrections | 2/2/2023 | ISIS ARGUETA |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 5/16/2025 | ROY SPAULDING |
| CofO Issued | 5/16/2025 | DEROLD HAUFF |
| Permit Finaled | 5/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/2/2022 | NELSON RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 10/20/2023 | ALFRED RAMIREZ |
Contact Information
| Contractor | John Crystal Pools; Lic. No.: 1008762-C27 | 9560 TOPANGA CANYON BLVD UNIT 202 CHATSWORTH, CA 91311 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/29/2024 | Corrections Issued | CRAIG VAUGHAN |
| Pre-Inspection | 5/29/2024 | Approved | CRAIG VAUGHAN |
| Deputy Shotcrete | 6/25/2024 | Conditional Approval | BRENDAN MORELLI |
| Gas Piping or Gas Test | 9/10/2024 | Approved | CRAIG VAUGHAN |
| Grounding or Bonding | 9/10/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Rough-Plumbing | 9/10/2024 | Approved | CRAIG VAUGHAN |
| Grounding or Bonding | 3/4/2025 | Approved | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 5/13/2025 | Approved | ROY SPAULDING |
| Final | 5/13/2025 | Corrections Issued | ROY SPAULDING |
| Pre-Gunite | 5/13/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Not Ready | ROY SPAULDING |
| Final | 5/15/2025 | OK to Issue CofO | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Approved | ROY SPAULDING |