537 S MORENO AVE 90049

Certificate Information: 537 S MORENO AVE 90049

Application / Permit
22047-20000-02105
Plan Check / Job No.
B22VN15467
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 35' X 17' POOL AND 10' X 9' SPA PER LACITY STANDARD PLAN #268 WITH SUPPLEMENTAL DETAILS #551 and #672 AND AUTOMATIC POOL VAULT COVER PER ENGINEERING.
Permit Issued
Issued on 10/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2022 APPLICANT
Assigned to Plan Check Engineer 10/17/2022 OMAR GARNICA
Corrections Issued 10/17/2022 OMAR GARNICA
Plan Check Approved 10/26/2022 SERGIO MUNIZ
Issued 10/26/2022 APPLICANT
CofO in Progress 7/31/2024 KIRK SANDERS
Permit Finaled 8/26/2024 RICHARD STEINBACH
CofO Issued 8/26/2024 RICHARD STEINBACH
Permit Finaled 8/26/2024 RICHARD STEINBACH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Exclusive Pools Inc; Lic. No.: 343762-C53 18017 CHATSWORTH ST      GRANADA HILLS, CA 91344
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/29/2022 Corrections Issued ASHLEY THOMPSON
Pre-Gunite 12/21/2022 Corrections Issued ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 12/29/2022 Approved ASHLEY THOMPSON
Pre-Gunite 12/29/2022 Approved ASHLEY THOMPSON
Rough-Electrical 12/29/2022 Approved ASHLEY THOMPSON
Rough-Plumbing 12/29/2022 Approved ASHLEY THOMPSON
Deputy Shotcrete 1/4/2023 Conditional Approval MICHAEL PELHAM
Grounding or Bonding 6/13/2023 Approved JESUS PINEDA
Enclosure/Fence 4/12/2024 Approved ASHLEY THOMPSON
Final 7/2/2024 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Not Ready KIRK SANDERS
Equipment Noise Level 7/9/2024 Approved EUSEBIO GUZMAN
Final 7/16/2024 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Approved KIRK SANDERS
Final 7/30/2024 OK to Issue CofO KIRK SANDERS