14935 W OTSEGO ST 91403
Certificate Information: 14935 W OTSEGO ST 91403
- Application / Permit
- 22047-20000-02099
- Plan Check / Job No.
- B22VN15423
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17' x 27' SWIMMING POOL WITH BAJA AND 6' X 7' SPA PER LACITY STANDARD PLAN 268
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2022 | OMAR GARNICA |
| Corrections Issued | 10/17/2022 | OMAR GARNICA |
| Plan Check Approved | 11/18/2022 | ISIS ARGUETA |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 5/14/2024 | JACK KARGODORIAN |
| Permit Finaled | 5/17/2024 | RUBEN SALAS |
| CofO Issued | 5/17/2024 | RUBEN SALAS |
| Permit Finaled | 5/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/19/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 5/1/2023 | Partial Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Conditional Approval | THOMAS FINNILA |
| Rough-Plumbing | 5/25/2023 | Partial Approval | THOMAS FINNILA |
| Pool Piping | 6/9/2023 | Partial Approval | THOMAS FINNILA |
| Grounding or Bonding | 9/27/2023 | Corrections Issued | THOMAS FINNILA |
| Grounding or Bonding | 10/3/2023 | Approved | THOMAS FINNILA |
| Enclosure/Fence | 10/5/2023 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 10/10/2023 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 10/13/2023 | Approved | THOMAS FINNILA |
| Pool Equipment Noise Test | 11/1/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 11/8/2023 | Approved | DANIEL ORRANTE |
| Final | 11/8/2023 | Corrections Issued | DANIEL ORRANTE |
| Pre-Gunite | 11/8/2023 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | DANIEL ORRANTE |
| Final | 11/27/2023 | Partial Approval | THOMAS FINNILA |
| Final | 4/8/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 5/14/2024 | OK to Issue CofO | JACK KARGODORIAN |