5900 N WINNETKA AVE 91367

Certificate Information: 5900 N WINNETKA AVE 91367

Application / Permit
22047-20000-02055
Plan Check / Job No.
B22VN15080
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AND SPA ON PILES WITH SLIDE; ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/16/2023
Issuing Office
Valley
Current Status
Issued on 3/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 SELLA BENYAMIN
Corrections Issued 10/17/2022 SELLA BENYAMIN
Quality Review Completed 10/19/2022 STEVEN KIM
Building Plans Picked Up 10/20/2022 APPLICANT
Applicant returned to address corrections 3/9/2023 SELLA BENYAMIN
Plan Check Approved 3/16/2023 SELLA BENYAMIN
Issued 3/16/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/27/2022 SELLA BENYAMIN
Eng Process Fee Ord 176,300 Cleared 12/27/2022 COLIN LOREDO
Work Adjacent to Public Way Cleared 12/27/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 2/28/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/26/2023 Corrections Issued JON MCHUGH
Piling/Pier/Caisson 6/26/2023 Not Ready for Inspection JON MCHUGH
Pre-Inspection 6/26/2023 Partial Approval JON MCHUGH
Special/Order Compliance 6/26/2023 Not Ready for Inspection HORACE FULTZ
Piling/Pier/Caisson 6/30/2023 Corrections Issued JON MCHUGH
Excavation/Setback/Form/Re-Bar 9/8/2023 Not Ready for Inspection JON MCHUGH
Piling/Pier/Caisson 9/8/2023 Corrections Issued JON MCHUGH
Excavation/Setback/Form/Re-Bar 9/25/2023 Partial Approval JON MCHUGH
Piling/Pier/Caisson 9/25/2023 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 12/17/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 12/18/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 2/2/2024 Corrections Issued JON MCHUGH
Excavation/Setback/Form/Re-Bar 2/7/2024 Corrections Issued JON MCHUGH
Pool Piping 2/7/2024 Corrections Issued JON MCHUGH
Excavation/Setback/Form/Re-Bar 2/9/2024 Partial Approval JON MCHUGH
Pool Piping 2/9/2024 Partial Approval JON MCHUGH
Pre-Gunite 2/9/2024 Partial Approval JON MCHUGH
Deputy Shotcrete 2/15/2024 Conditional Approval JON MCHUGH
Rough-Plumbing 3/20/2024 Not Ready for Inspection JON MCHUGH
Pool Piping 3/22/2024 Not Ready for Inspection JON MCHUGH
Rough-Plumbing 3/22/2024 Not Ready for Inspection JON MCHUGH
Pool Piping 3/27/2024 Partial Inspection JOHN KIDWELL
Deputy Other (see comments) 9/23/2024 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 9/24/2024 Partial Approval JON MCHUGH
Piling/Pier/Caisson 9/24/2024 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 10/18/2024 Partial Approval JON MCHUGH
Deputy Other (see comments) 10/21/2024 Conditional Approval JON MCHUGH
Deputy Other (see comments) 12/13/2024 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 12/16/2024 Approved MORRIS JACKSON
Gunite 12/16/2024 Not Ready for Inspection MORRIS JACKSON
Rough-Electrical 12/16/2024 Approved MORRIS JACKSON
Rough-Plumbing 12/16/2024 Approved MORRIS JACKSON
Deputy Other (see comments) 12/17/2024 Conditional Approval MORRIS JACKSON
Gunite 12/17/2024 Approved MORRIS JACKSON
Deputy Shotcrete 12/20/2024 Partial Approval SEAN WIRCH
Deputy Other (see comments) 2/12/2025 Approved JON MCHUGH
Excavation/Setback/Form/Re-Bar 2/12/2025 Partial Approval JON MCHUGH
Gas Piping or Gas Test 2/12/2025 Corrections Issued JON MCHUGH
Deck 2/14/2025 Corrections Issued JON MCHUGH
Gas Piping or Gas Test 2/14/2025 Not Ready for Inspection JON MCHUGH
Deck 2/24/2025 Partial Approval JON MCHUGH
Gas Piping or Gas Test 2/24/2025 Partial Approval JON MCHUGH
Piling/Pier/Caisson 2/24/2025 Approved JON MCHUGH
Deputy Other (see comments) 3/4/2025 Conditional Approval JON MCHUGH
Deputy Drilled-In Anchors 3/20/2025 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 3/25/2025 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 4/15/2025 Corrections Issued JON MCHUGH
Deck 5/2/2025 Partial Approval JON MCHUGH
ELECTRICAL-Final 6/18/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 6/18/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 7/8/2025 Not Ready for Inspection JON MCHUGH
Enclosure/Fence 7/8/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 7/8/2025 Not Ready for Inspection JON MCHUGH
Enclosure/Fence 7/10/2025 Corrections Issued JON MCHUGH
Enclosure/Fence 7/11/2025 Approved JON MCHUGH
Excavation/Setback/Form/Re-Bar 2/12/2026 Approved JON MCHUGH
Final 2/12/2026 Corrections Issued JON MCHUGH
Pre-Gunite 2/12/2026 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Approved JON MCHUGH
Pool Equipment Noise Test 2/19/2026 Approved ALFREDO FLORES