11002 N SWEETWATER CT 91311
Certificate Information: 11002 N SWEETWATER CT 91311
- Application / Permit
- 22047-20000-01985
- Plan Check / Job No.
- B22VN14635
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20' x 38.5 POOL AND 8'-0" X 10'-0" SPA PER LA STANDARD PLAN# 268 AND SUPPLEMENTAL DETAIL 650.
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | JESSE ARELLANO |
| Corrections Issued | 9/29/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/20/2022 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 11/1/2022 | LUIS RINCON |
| Issued | 11/1/2022 | APPLICANT |
| CofO in Progress | 8/23/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/20/2025 | MICHAEL PELHAM |
| CofO Issued | 9/20/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/20/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/20/2022 | MIROOSH KHACHATOORIAN |
| Tract Map conditions | Cleared | 10/21/2022 | BRENNEN OBETO |
Contact Information
| Contractor | Esther Construction Inc; Lic. No.: 695716-C53 | 15224 FOOTHILL BLVD SYLMAR, CA 91342 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/16/2023 | Approved | DAVID SCANTLIN |
| Deputy Shotcrete | 3/31/2023 | Partial Approval | JOHN KIDWELL |
| Deck | 5/26/2023 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 11/14/2023 | Approved | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Approved | DAVID SCANTLIN |
| Final | 1/12/2024 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Approved | DAVID SCANTLIN |
| Equipment Noise Level | 1/17/2024 | Approved | ALFREDO FLORES |
| Final | 8/23/2025 | OK to Issue CofO | MICHAEL PELHAM |