6600 W 80TH PL 90045
Certificate Information: 6600 W 80TH PL 90045
- Application / Permit
- 22047-20000-01968
- Plan Check / Job No.
- B22VN14513
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12' X 33'-6" POOL W/ 12' X 5' SPA PER LA CITY STD PLAN No. 270
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2022 | RAMA DABADGE |
| Corrections Issued | 9/27/2022 | RAMA DABADGE |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 5/7/2024 | BOBBY KEY |
| Permit Finaled | 5/7/2024 | DANIEL ORRANTE |
| CofO Issued | 5/7/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/7/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/1/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Royal Moon Pools Inc; Lic. No.: 1041907-C53 | P O BOX 1044 ROSAMOND, CA 93560 |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Approved | BOBBY KEY |
| Final | 6/21/2023 | Corrections Issued | BOBBY KEY |
| Grounding or Bonding | 6/21/2023 | Partial Approval | BOBBY KEY |
| Pool Piping | 6/21/2023 | Conditional Approval | BOBBY KEY |
| Pre-Gunite | 6/21/2023 | Approved | BOBBY KEY |
| Grounding or Bonding | 8/30/2023 | Approved | BOBBY KEY |
| Enclosure/Fence | 12/4/2023 | Corrections Issued | BOBBY KEY |
| Enclosure/Fence | 12/6/2023 | Corrections Issued | BOBBY KEY |
| Enclosure/Fence | 12/14/2023 | Corrections Issued | BOBBY KEY |
| Enclosure/Fence | 12/22/2023 | Conditional Approval | KENNETH NAGLE |
| Pool Equipment Noise Test | 3/19/2024 | Approved | JAMES VORHIS |
| Final | 4/3/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/12/2024 | Not Ready for Inspection | BOBBY KEY |
| Final | 4/12/2024 | Corrections Issued | BOBBY KEY |
| Final | 4/19/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Final | 5/6/2024 | OK to Issue CofO | BOBBY KEY |