20248 W WILLOUGHBY LANE 91326
Certificate Information: 20248 W WILLOUGHBY LANE 91326
- Application / Permit
- 22047-20000-01864
- Plan Check / Job No.
- B22VN13649
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan New swimming pool and spa.
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Current Status
- Issued on 11/10/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 9/27/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 10/11/2022 | ZAW HAN |
| Plan Check Approved | 11/7/2022 | SAMUEL GONZALEZ |
| Issued | 11/10/2022 | APPLICANT |
Permit Application Clearance Information
| "T" removal | Cleared | 10/17/2022 | KENTON TRINH |
| ZA Case | Cleared | 10/17/2022 | KENTON TRINH |
| ZA Case | Cleared | 10/17/2022 | KENTON TRINH |
| Low Impact Development | Cleared | 10/20/2022 | ROGELIO CORTES |
Contact Information
| Contractor | Calimingo Pools Inc; Lic. No.: 919876-C53 | , |
| Contractor | Proscapes Oc; Lic. No.: 919876-C53 | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/17/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Shotcrete | 11/22/2022 | Approved | JEFFREY PARD |
| Deck | 12/27/2022 | Approved | STEVEN BACK |
| Enclosure/Fence | 4/19/2023 | Corrections Issued | DAVID SCANTLIN |
| Pre-Gunite | 4/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Enclosure/Fence | 4/26/2023 | Approved | STEVEN BACK |
| Final | 4/26/2023 | Corrections Issued | STEVEN BACK |
| Pre-Gunite | 4/26/2023 | Approved | STEVEN BACK |
| Pool Equipment Noise Test | 5/10/2023 | Approved | KIM BEAUCHAMP |
| Excavation/Setback/Form/Re-Bar | 5/16/2023 | Approved | DAVID SCANTLIN |
| Final | 5/16/2023 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | DAVID SCANTLIN |