4356 N ALLOTT AVE 91423
Certificate Information: 4356 N ALLOTT AVE 91423
- Application / Permit
- 22047-20000-01745
- Plan Check / Job No.
- B22VN12906
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 30' SWIMMING POOL WITH 7' X 7' SPA PER ENGINEERING
- Permit Issued
- Issued on 1/24/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | SELLA BENYAMIN |
| Corrections Issued | 9/15/2022 | SELLA BENYAMIN |
| Quality Review Completed | 9/15/2022 | STEVEN KIM |
| Building Plans Picked Up | 9/19/2022 | APPLICANT |
| Plan Check Approved | 1/24/2023 | SELLA BENYAMIN |
| Issued | 1/24/2023 | APPLICANT |
| CofO in Progress | 8/22/2023 | MISAEL ESPARZA |
| Permit Finaled | 9/27/2023 | RUBEN SALAS |
| CofO Issued | 9/27/2023 | RUBEN SALAS |
| Permit Finaled | 9/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/12/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Basen Construction Inc; Lic. No.: 1074082-B | 201 N REESE PL UNIT 101 BURBANK, CA 91506 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Corrections Issued | MISAEL ESPARZA |
| Pool Piping | 4/25/2023 | Approved | MISAEL ESPARZA |
| Deputy Shotcrete | 4/26/2023 | Conditional Approval | MISAEL ESPARZA |
| Gas Piping or Gas Test | 6/14/2023 | Approved | JOHN COLEMAN |
| Rough-Electrical | 6/14/2023 | Approved | JOHN COLEMAN |
| Rough-Plumbing | 6/14/2023 | Approved | JOHN COLEMAN |
| Deck | 7/24/2023 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 7/24/2023 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/10/2023 | Approved | MISAEL ESPARZA |
| Final | 8/10/2023 | Corrections Issued | MISAEL ESPARZA |
| Pre-Gunite | 8/10/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | MISAEL ESPARZA |
| Equipment Noise Level | 8/11/2023 | Approved | ALFREDO FLORES |
| Final | 8/15/2023 | Conditional Approval | MISAEL ESPARZA |
| Final | 8/18/2023 | OK to Issue CofO | MISAEL ESPARZA |