1743 S CLUB VIEW DR 90024
Certificate Information: 1743 S CLUB VIEW DR 90024
- Application / Permit
- 22047-20000-01715
- Plan Check / Job No.
- B22VN12678
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 26'-6" X 16'-8 1/2" POOL WITH 6'-6" X 16'-8 1/2" SPA PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/18/2022 | ALEC MOUSAKHANIAN |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 5/24/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
| CofO Issued | 6/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 7361 ETHEL AVE SUITE 4 NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/26/2022 | Corrections Issued | CARLOS MATAMOROS |
| Rough-Plumbing | 10/21/2022 | Corrections Issued | STEPHANIE SWANSON |
| Rough-Plumbing | 11/14/2022 | Partial Approval | MICHAEL PELHAM |
| Deck | 2/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Gunite | 2/21/2023 | Approved | STEPHANIE SWANSON |
| Deputy Shotcrete | 2/23/2023 | Conditional Approval | MICHAEL PELHAM |
| Gas Piping or Gas Test | 4/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Not Ready | STEPHANIE SWANSON |
| Gas Piping or Gas Test | 6/14/2024 | Approved | STEPHANIE SWANSON |
| Deck | 7/3/2024 | Partial Approval | CARLOS MATAMOROS |
| Enclosure/Fence | 9/24/2024 | Approved | STEPHANIE SWANSON |
| Equipment Noise Level | 5/13/2025 | Approved | ANDEY CHAPARRO |
| Pool Equipment Noise Test | 5/13/2025 | Approved | ANDEY CHAPARRO |
| Final | 5/15/2025 | OK to Issue CofO | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Approved | DANIEL VERA |