10511 N MARY BELL AVE 91040
Certificate Information: 10511 N MARY BELL AVE 91040
- Application / Permit
- 22047-20000-01689
- Plan Check / Job No.
- B22VN12448
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 22' x 40' SWIMMING POOL/ SPA ON PILES W/ A WATERFALL WALL; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | SEAN SHAHMIRI |
| Corrections Issued | 8/22/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 8/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/25/2022 | APPLICANT |
| Plan Check Approved | 5/30/2023 | SEAN SHAHMIRI |
| Issued | 6/6/2023 | APPLICANT |
| CofO in Progress | 5/6/2025 | DAVID ANDERSON |
| Permit Finaled | 5/22/2025 | RUBEN SALAS |
| CofO Issued | 5/22/2025 | RUBEN SALAS |
| Permit Finaled | 5/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/6/2022 | BRENNEN OBETO |
| Miscellaneous | Cleared | 9/6/2022 | BRENNEN OBETO |
| Miscellaneous | Cleared | 9/6/2022 | BRENNEN OBETO |
| Miscellaneous | Cleared | 9/6/2022 | BRENNEN OBETO |
| Miscellaneous | Cleared | 9/6/2022 | BRENNEN OBETO |
| Miscellaneous | Cleared | 9/6/2022 | BRENNEN OBETO |
| ZI | Cleared | 9/19/2022 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Voskanian Razmik Thomas; Lic. No.: 909850-B | 2330 N SPARKS STREET BURBANK, CA 91504 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Geologist | Zweigler,, Robert Ingraham; Lic. No.: EG1210 | 196 DIRT ROAD THOUSAND OAKS, CA 91361 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 8/28/2023 | Conditional Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 8/29/2023 | Partial Approval | DAVID ANDERSON |
| Deputy Other (see comments) | 9/27/2023 | Conditional Approval | DAVID MATSON |
| Pre-Gunite | 4/17/2024 | Corrections Issued | DAVID ANDERSON |
| Rough-Electrical | 4/17/2024 | Approved | DAVID ANDERSON |
| Rough-Plumbing | 4/17/2024 | Approved | DAVID ANDERSON |
| Posting Pre-Inspection | 4/22/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Deputy Shotcrete | 5/1/2024 | Conditional Approval | DAVID MATSON |
| Rough-Electrical | 5/1/2024 | Approved | DAVID ANDERSON |
| Rough-Plumbing | 5/1/2024 | Approved | DAVID ANDERSON |
| Deck | 10/24/2024 | Approved | DAVID ANDERSON |
| Grounding or Bonding | 10/24/2024 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 2/4/2025 | Approved | DAVID ANDERSON |
| Final | 2/4/2025 | Corrections Issued | DAVID ANDERSON |
| Pre-Gunite | 2/4/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | DAVID ANDERSON |
| Pool Equipment Noise Test | 3/19/2025 | Approved | FELIPE PENICHE |
| Final | 4/18/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/25/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 5/5/2025 | OK to Issue CofO | DAVID ANDERSON |