2169 N ROSCOMARE ROAD 90077
Certificate Information: 2169 N ROSCOMARE ROAD 90077
- Application / Permit
- 22047-20000-01657
- Plan Check / Job No.
- B22VN12221
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14'-0" x 26'-0" POOL AND 6'-0"x 6'-0" SPA PER LA CITY STANDARD PLAN # 268.
- Permit Issued
- Issued on 11/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2022 | LUIS RINCON |
| Corrections Issued | 8/16/2022 | LUIS RINCON |
| Plan Check Approved | 11/17/2022 | MIROOSH KHACHATOORIAN |
| Issued | 11/17/2022 | APPLICANT |
| CofO in Progress | 10/6/2023 | CARLOS MATAMOROS |
| CofO in Progress | 10/6/2023 | CARLOS MATAMOROS |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
| CofO Issued | 10/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/17/2022 | MIROOSH KHACHATOORIAN |
Contact Information
| Contractor | Lax Home Inc; Lic. No.: 1063552-B | 15021 VENTURA BLVD STE 810 SHERMAN OAKS, CA 91403 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/5/2022 | Approved | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 12/5/2022 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 12/5/2022 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 12/5/2022 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 12/5/2022 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 12/5/2022 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 12/7/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deck | 1/23/2023 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 1/23/2023 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 4/26/2023 | Approved | CARLOS MATAMOROS |
| Equipment Noise Level | 6/27/2023 | No Access for Inspection | ZEYDI STEWART |
| Equipment Noise Level | 8/17/2023 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Final | 9/20/2023 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Equipment Noise Level | 9/26/2023 | Approved | JUAN ESCOTO DELGADO |
| ELECTRICAL-Final | 10/5/2023 | Approved | CARLOS MATAMOROS |
| Final | 10/5/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| PLUMBING-Final | 10/5/2023 | Approved | CARLOS MATAMOROS |