11728 N MANCHESTER WAY 91326

Certificate Information: 11728 N MANCHESTER WAY 91326

Application / Permit
22047-20000-01655
Plan Check / Job No.
B22VN12212
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' x 27' POOL AND 8' x 8' SPA AND RAISED BOND BEAM PER STD. PLAN # 268 AND ENG DETAILS
Permit Issued
Issued on 8/30/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/9/2022 JEFFREY TANGONAN
Corrections Issued 8/9/2022 JEFFREY TANGONAN
Plan Check Approved 8/26/2022 YAQUB MIRZA
Issued 8/30/2022 APPLICANT
CofO in Progress 8/1/2023 STEVEN BACK
Permit Finaled 8/9/2023 JOHN JANSON
CofO Issued 8/9/2023 JOHN JANSON
Permit Finaled 8/9/2023 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 8/11/2022 BRENNEN OBETO
Miscellaneous Cleared 8/11/2022 BRENNEN OBETO
ZA Case Cleared 8/11/2022 BRENNEN OBETO
ZA Case Cleared 8/11/2022 BRENNEN OBETO

Contact Information

Contractor P & J Construction Co; Lic. No.: 949334-B 4120 WISHING HILL DRIVE      LA CANADA, CA 91011
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2022 Approved JEFFREY PARD
Pre-Gunite 10/24/2022 Approved JEFFREY PARD
Gas Piping or Gas Test 12/30/2022 Corrections Issued STEVEN BACK
Deck 2/3/2023 Corrections Issued STEVEN BACK
Deck 2/9/2023 Partial Approval STEVEN BACK
Enclosure/Fence 6/16/2023 Corrections Issued STEVEN BACK
Enclosure/Fence 7/11/2023 Corrections Issued STEVEN BACK
Special/Order Compliance 7/11/2023 Approved HORACE FULTZ
Deputy Other (see comments) 7/21/2023 Corrections Issued STEVEN BACK
Enclosure/Fence 7/21/2023 Approved STEVEN BACK
Deputy Shotcrete 7/24/2023 Conditional Approval HENRY KIM
Final 7/27/2023 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Approved STEVEN BACK
Pool Equipment Noise Test 7/31/2023 Approved ALFREDO FLORES
ELECTRICAL-Final 8/1/2023 Approved STEVEN BACK
Final 8/1/2023 OK to Issue CofO STEVEN BACK
Rough-Plumbing 8/1/2023 Approved STEVEN BACK