20600 W HUMMINGBIRD CT 91326

Certificate Information: 20600 W HUMMINGBIRD CT 91326

Application / Permit
22047-20000-01551
Plan Check / Job No.
B22VN11632
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan New Pool and spa and Baja Pool size 8'x27' spa size 6'x6' baja size 5'x7' 1 OF 2
Permit Issued
Issued on 8/10/2022
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 JOSEPH RAFOLS
Corrections Issued 7/29/2022 JOSEPH RAFOLS
Plan Check Approved 8/5/2022 JOSEPH RAFOLS
Issued 8/10/2022 APPLICANT
CofO in Progress 12/14/2023 STEVEN BACK
No Progress 12/15/2023 STEVEN BACK
CofO in Progress 12/15/2023 STEVEN BACK
CofO in Progress 2/13/2024 STEVEN BACK
Permit Finaled 3/6/2024 JOHN JANSON
CofO Issued 3/6/2024 JOHN JANSON

Permit Application Clearance Information

"T" removal Cleared 8/2/2022 ASHLEY RODARTE
Specific Plan Cleared 8/2/2022 ASHLEY RODARTE
ZA Case Cleared 8/2/2022 ASHLEY RODARTE
ZA Case Cleared 8/2/2022 ASHLEY RODARTE

Contact Information

Contractor Joe Uko Inc; Lic. No.: 1035168-B 11336 CAMARILLO ST #310      NORTH HOLLYWOOD, CA 91601

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2022 Approved DAVID SCANTLIN
Grounding or Bonding 11/17/2022 Approved DAVID SCANTLIN
Pool Piping 11/17/2022 Approved DAVID SCANTLIN
Pre-Gunite 11/17/2022 Approved DAVID SCANTLIN
Rough-Electrical 11/17/2022 Approved DAVID SCANTLIN
Rough-Plumbing 11/17/2022 Approved DAVID SCANTLIN
Deputy Shotcrete 11/29/2022 Conditional Approval DAVID SCANTLIN
Deck 2/9/2023 Approved KRISTEN CAUSEY
Enclosure/Fence 2/9/2023 Approved KRISTEN CAUSEY
Pool Equipment Noise Test 8/21/2023 Approved FELIPE PENICHE
Final 9/5/2023 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Approved STEVEN BACK
Final 12/14/2023 Corrections Issued STEVEN BACK
Final 12/15/2023 Corrections Issued STEVEN BACK
Final 2/13/2024 OK to Issue CofO STEVEN BACK