11142 W KLING ST 91602
Certificate Information: 11142 W KLING ST 91602
- Application / Permit
- 22047-20000-01501
- Plan Check / Job No.
- B22VN11305
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN 1) Proposed 399 SF Pool. 2) 38 SF Jacuzzi PER ENGINEERING
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/25/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/1/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 10/6/2022 | MAHNAZ NOURHASHEMI |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 1/27/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
| CofO Issued | 3/13/2025 | RUBEN SALAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2023 | Approved | JACK KARGODORIAN |
| Pool Piping | 5/17/2023 | Approved | JACK KARGODORIAN |
| Pre-Gunite | 5/17/2023 | Approved | JACK KARGODORIAN |
| Rough-Electrical | 5/17/2023 | Approved | JACK KARGODORIAN |
| Enclosure/Fence | 1/17/2024 | Approved | KIRK SANDERS |
| Gas Piping or Gas Test | 1/17/2024 | Approved | KIRK SANDERS |
| Grounding or Bonding | 1/17/2024 | Approved | KIRK SANDERS |
| Final | 5/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pool Equipment Noise Test | 5/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 5/7/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pool Equipment Noise Test | 5/7/2024 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Final | 11/20/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 1/27/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |