8317 N STEPHEN LANE 91304

Certificate Information: 8317 N STEPHEN LANE 91304

Application / Permit
22047-20000-01463
Plan Check / Job No.
B22VN11048
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 22' X 38' POOL W/ 8' X 8' SPA INSIDE PER ENGINEERING.
Permit Issued
Issued on 2/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 RAPHAEL ROSAS
Corrections Issued 8/11/2022 RAPHAEL ROSAS
Quality Review Completed 8/12/2022 STEVEN KIM
Building Plans Picked Up 8/15/2022 APPLICANT
Plan Check Approved 2/21/2023 RAPHAEL ROSAS
Issued 2/21/2023 APPLICANT
CofO in Progress 5/13/2026 JEFFREY HARTLINE
Permit Finaled 5/21/2026 JOHN JANSON
CofO Issued 5/21/2026 JOHN JANSON
Permit Finaled 5/21/2026 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 1/23/2023 BRENNEN OBETO
Construction near power lines Cleared 2/9/2023 NADER ISKANDER
Grading Pre-Inspection Cleared 2/21/2023 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2023 Corrections Issued CHRIS CHRISTENSEN
Pool Piping 9/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Electrical 9/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Plumbing 9/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Grounding or Bonding 9/29/2023 Approved JEFFREY HARTLINE
Pool Piping 9/29/2023 Approved JEFFREY HARTLINE
Rough-Electrical 9/29/2023 Approved JEFFREY HARTLINE
Rough-Plumbing 9/29/2023 Approved JEFFREY HARTLINE
Deputy Shotcrete 10/4/2023 Partial Approval JEFFREY HARTLINE
Gas Piping or Gas Test 12/4/2023 Approved JEFFREY HARTLINE
Grounding or Bonding 12/4/2023 Approved JEFFREY HARTLINE
Enclosure/Fence 4/10/2024 Corrections Issued JEFFREY HARTLINE
Enclosure/Fence 4/11/2024 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 8/19/2025 Approved JEFFREY HARTLINE
Final 8/19/2025 OK to Issue CofO JEFFREY HARTLINE
Pre-Gunite 8/19/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved JEFFREY HARTLINE