13890 N GARRICK AVE 91342
Certificate Information: 13890 N GARRICK AVE 91342
- Application / Permit
- 22047-20000-01448
- Plan Check / Job No.
- B22VN10908
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 38'-0" X 17'-4" POOL W/ 10'-1" X 9'-2" SPA PER STD PLAN # 268 & ENGINEERING DETAILS (1 of 3)
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 7/16/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Applicant returned to address corrections | 1/6/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 1/12/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/17/2023 | ALEC MOUSAKHANIAN |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 6/6/2023 | MICHEL ABAJAN |
| CofO Issued | 6/9/2023 | MICHAEL SMITH |
| Permit Finaled | 6/9/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 7/25/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 7/25/2022 | BRENNEN OBETO |
Contact Information
| Contractor | Pacific Outdoor Living; Lic. No.: 715731-C27 | 8309 TUJUNGA AVE SUITE 201 SUN VALLEY, CA 91352 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Approved | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 4/10/2023 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 4/10/2023 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 4/10/2023 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 4/10/2023 | Approved | ARAM AVEDISIAN |
| Rough-Electrical | 4/10/2023 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 4/11/2023 | Conditional Approval | ARAM AVEDISIAN |
| Deck | 4/26/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Grounding or Bonding | 4/26/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Enclosure/Fence | 5/12/2023 | Approved | ARAM AVEDISIAN |
| Pool Equipment Noise Test | 5/26/2023 | Approved | ALFREDO FLORES |
| Final | 5/30/2023 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/6/2023 | Approved | MICHEL ABAJAN |
| Final | 6/6/2023 | OK to Issue CofO | MICHEL ABAJAN |
| PLUMBING-Final | 6/6/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | MICHEL ABAJAN |