17847 W CATHEDRAL PL 91316

Certificate Information: 17847 W CATHEDRAL PL 91316

Application / Permit
22047-20000-01422
Plan Check / Job No.
B22VN10701
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 50' X 16' POOL AND 9' X 12' SPA PER ENGINEERING
Permit Issued
Issued on 11/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 SELLA BENYAMIN
Corrections Issued 7/25/2022 SELLA BENYAMIN
Quality Review Completed 7/29/2022 STEVEN KIM
Building Plans Picked Up 8/10/2022 APPLICANT
Plan Check Approved 11/4/2022 SELLA BENYAMIN
Issued 11/4/2022 APPLICANT
CofO in Progress 4/4/2024 JOHN KIDWELL
Permit Finaled 7/9/2024 JOHN JANSON
CofO Issued 7/9/2024 JOHN JANSON
Permit Finaled 7/9/2024 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 3/9/2023 Partial Approval DAVID SANDOVAL
Piling/Pier/Caisson 3/9/2023 Corrections Issued DAVID SANDOVAL
Piling/Pier/Caisson 3/17/2023 Approved DAVID SANDOVAL
Deputy Other (see comments) 3/20/2023 Conditional Approval DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 5/17/2023 Partial Approval SEAN HAUPT
Deputy Other (see comments) 5/23/2023 Approved SEAN HAUPT
Pre-Gunite 6/23/2023 Approved SEAN HAUPT
Gas Piping or Gas Test 6/27/2023 Approved SEAN HAUPT
Rough-Electrical 6/27/2023 Approved SEAN HAUPT
Rough-Plumbing 6/27/2023 Approved SEAN HAUPT
Deputy Shotcrete 7/5/2023 Approved SEAN HAUPT
Deck 9/21/2023 Not Ready for Inspection JEFFREY PARD
Grounding or Bonding 9/21/2023 Partial Approval JEFFREY PARD
Deck 10/2/2023 Approved SEAN HAUPT
Grounding or Bonding 10/2/2023 Approved SEAN HAUPT
Special/Order Compliance 10/2/2023 Corrections Issued SEAN HAUPT
Enclosure/Fence 2/8/2024 Corrections Issued SEAN HAUPT
Enclosure/Fence 2/26/2024 Approved JOHN KIDWELL
ELECTRICAL-Final 3/20/2024 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/20/2024 Approved JOHN KIDWELL
Final 3/20/2024 Corrections Issued JOHN KIDWELL
PLUMBING-Final 3/20/2024 Approved JOHN KIDWELL
Pool Equipment Noise Test 3/20/2024 Approved ALFREDO FLORES
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Approved JOHN KIDWELL
Final 4/2/2024 OK to Issue CofO JOHN KIDWELL
Enclosure/Fence 6/27/2024 Approved JOHN KIDWELL