15903 W SUNBURST ST 91343
Certificate Information: 15903 W SUNBURST ST 91343
- Application / Permit
- 22047-20000-01420
- Plan Check / Job No.
- B22VN10665
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW IRREGULAR SHAPED 17' X 33' SWIMMING POOL WTH 10'-3" ROUND SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | JESSE ARELLANO |
| Corrections Issued | 7/13/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 5/30/2023 | RAUL OLAGI |
| Permit Finaled | 6/5/2023 | MICHAEL SMITH |
| CofO Issued | 6/5/2023 | MICHAEL SMITH |
| Permit Finaled | 6/5/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/15/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/11/2022 | Conditional Approval | RAUL OLAGI |
| Deputy Shotcrete | 10/17/2022 | Conditional Approval | RAUL OLAGI |
| Deck | 4/20/2023 | Approved | RAUL OLAGI |
| Deputy Shotcrete | 4/20/2023 | Corrections Issued | RAUL OLAGI |
| Enclosure/Fence | 4/26/2023 | Conditional Approval | RAUL OLAGI |
| Special/Order Compliance | 4/26/2023 | Corrections Issued | RAUL OLAGI |
| Equipment Noise Level | 5/17/2023 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Approved | RAUL OLAGI |
| Final | 5/22/2023 | Corrections Issued | RAUL OLAGI |
| Pre-Gunite | 5/22/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Approved | RAUL OLAGI |
| Final | 5/30/2023 | OK to Issue CofO | RAUL OLAGI |