3945 S BEETHOVEN ST 90066
Certificate Information: 3945 S BEETHOVEN ST 90066
- Application / Permit
- 22047-20000-01349
- Plan Check / Job No.
- B22VN10052
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 29' X 16' POOL AND 5' X 9' SPA WITHIN PER STANDARD PLAN #268
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Current Status
- CofO Issued on 9/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 7/1/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 7/13/2022 | LUIS RINCON |
| Plan Check Approved | 7/26/2022 | JEROME MAGAT PALMA |
| Issued | 7/26/2022 | APPLICANT |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| CofO in Progress | 9/12/2023 | HERBERT GIRON |
| Permit Finaled | 9/15/2023 | DANIEL ORRANTE |
| CofO Issued | 9/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/12/2022 | JEFF FOLLIN |
Contact Information
| Contractor | Amazon Pools; Lic. No.: 830886-C53 | 18653 VENTURA BLVD #139 TARZANA, CA 91356 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Rough-Electrical | 9/28/2022 | Partial Approval | JESUS RODRIGUEZ |
| Rough-Plumbing | 9/28/2022 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Shotcrete | 10/3/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Enclosure/Fence | 3/17/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Piping or Gas Test | 3/17/2023 | Approved | JESUS RODRIGUEZ |
| Pre-Gunite | 3/17/2023 | Approved | JESUS RODRIGUEZ |
| Rough-Electrical | 3/17/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Rough-Plumbing | 3/17/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/17/2023 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 7/14/2023 | Approved | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Approved | HERBERT GIRON |
| Final | 7/14/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | HERBERT GIRON |
| Final | 9/11/2023 | OK to Issue CofO | HERBERT GIRON |