10531 W VALLEY SPRING LANE 91602
Certificate Information: 10531 W VALLEY SPRING LANE 91602
- Application / Permit
- 22047-20000-01279
- Plan Check / Job No.
- B22VN09537
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan new swimming pool / spa
- Permit Issued
- Issued on 7/26/2023
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2022 | SUNMIN LEE |
| Corrections Issued | 6/23/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 10/26/2022 | SUNMIN LEE |
| Plan Check Approved | 10/28/2022 | SUNMIN LEE |
| Issued | 7/26/2023 | APPLICANT |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 8/9/2023 | Partial Approval | JACK KARGODORIAN |
| Gas Piping or Gas Test | 10/17/2023 | Approved | CHRISTOPHE COCHRAN |
| Gas Piping or Gas Test | 10/17/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Grounding or Bonding | 11/16/2023 | Partial Approval | JOSE AVILA |
| Gas Piping or Gas Test | 12/7/2023 | Partial Approval | KIRK SANDERS |
| Enclosure/Fence | 2/7/2024 | Approved | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/23/2024 | Approved | KIRK SANDERS |
| Final | 2/23/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | KIRK SANDERS |
| Pool Equipment Noise Test | 2/27/2024 | Approved | FELIPE PENICHE |
| Final | 2/29/2024 | Corrections Issued | KIRK SANDERS |
| Final | 3/15/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 3/21/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 3/26/2024 | Partial Approval | CHRISTOPHER ROJAS |