822 W UPLAND AVE 90731
Certificate Information: 822 W UPLAND AVE 90731
- Application / Permit
- 22047-20000-01274
- Plan Check / Job No.
- B22VN09518
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12'-0" X 9'-0" SWIMMING POOL W/ 7'-0" X 9'-0" SPA PER STD PLAN # 268 WITH & ENGINEERING DETAILS.
- Permit Issued
- Issued on 8/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 6/24/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 7/23/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Issued | 8/8/2022 | APPLICANT |
| CofO in Progress | 12/30/2022 | EUGENE CASSIDY |
| Permit Finaled | 12/30/2022 | ANSON MAGLASANG |
| CofO Issued | 12/30/2022 | ANSON MAGLASANG |
| Permit Finaled | 12/30/2022 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/8/2022 | ALFRED RAMIREZ |
Contact Information
| Contractor | Framework Construction & Remodeling Inc; Lic. No.: 1055261-B | 20720 VENTURA BLVD #270 WOODLAND HILLS, CA 91364 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/19/2022 | Approved | ANSON MAGLASANG |
| Pre-Gunite | 9/19/2022 | Approved | ANSON MAGLASANG |
| Rough-Electrical | 9/19/2022 | Approved | ANSON MAGLASANG |
| Rough-Plumbing | 9/19/2022 | Approved | ANSON MAGLASANG |
| Grounding or Bonding | 10/17/2022 | Approved | ANSON MAGLASANG |
| Enclosure/Fence | 11/2/2022 | Corrections Issued | ANSON MAGLASANG |
| Enclosure/Fence | 11/10/2022 | Approved | ANSON MAGLASANG |
| Final | 11/29/2022 | Corrections Issued | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | ANSON MAGLASANG |
| Equipment Noise Level | 12/6/2022 | Approved | AGUSTIN ALVAREZMORALES |
| ELECTRICAL-Final | 12/7/2022 | Approved | EUGENE CASSIDY |
| Final | 12/7/2022 | OK to Issue CofO | EUGENE CASSIDY |