6133 W 75TH ST 90045
Certificate Information: 6133 W 75TH ST 90045
- Application / Permit
- 22047-20000-01245
- Plan Check / Job No.
- B22VN09400
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' 4" X 23' 6" POOL WITH 7' X 7' SPA PER LA CITY STANDARD PLAN #268 AND ENGINEERED DETAIL #240
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | JESSE ARELLANO |
| Corrections Issued | 6/22/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 6/23/2022 | APPLICANT |
| Applicant returned to address corrections | 9/14/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/16/2022 | GURUNATH NESARAJAH |
| Issued | 9/16/2022 | APPLICANT |
| CofO in Progress | 8/15/2024 | BOBBY KEY |
| Permit Finaled | 8/16/2024 | RICHARD STEINBACH |
| CofO Issued | 8/16/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/16/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/14/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Royal Globe Construction Corporation; Lic. No.: 1049671-C53 | 5967 W 3RD STREET SUITE 370 LOS ANGELES, CA 90036 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/7/2022 | Corrections Issued | BOBBY KEY |
| Rough-Plumbing | 8/9/2023 | Corrections Issued | BOBBY KEY |
| Deputy Shotcrete | 10/11/2023 | Conditional Approval | RICHARD STEINBACH |
| Deck | 10/20/2023 | Approved | BOBBY KEY |
| Enclosure/Fence | 12/4/2023 | Corrections Issued | BOBBY KEY |
| Pre-Gunite | 12/4/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 12/4/2023 | Corrections Issued | BOBBY KEY |
| Enclosure/Fence | 1/31/2024 | Conditional Approval | BOBBY KEY |
| Pool Equipment Noise Test | 4/4/2024 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | Approved | BOBBY KEY |
| Final | 6/10/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Approved | BOBBY KEY |
| Final | 8/15/2024 | OK to Issue CofO | BOBBY KEY |