1524 S WALNUT AVE 90291
Certificate Information: 1524 S WALNUT AVE 90291
- Application / Permit
- 22047-20000-01243
- Plan Check / Job No.
- B22VN09372
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 32' SWIMMING POOLWITH ATTACHED 6' X 10' SPA W/ AUTO POOL COVER AS PER STANDARD PLAN # 268 AND ENGINEERING DETAILS 672
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | RARES BODEA |
| Corrections Issued | 6/21/2022 | RARES BODEA |
| Building Plans Picked Up | 6/23/2022 | APPLICANT |
| Plan Check Approved | 8/17/2022 | SERGIO MUNIZ |
| Issued | 8/17/2022 | APPLICANT |
| CofO in Progress | 1/12/2023 | EVAN COOPER |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
| CofO Issued | 1/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/4/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/4/2022 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 8/17/2022 | MATTHEW JENKINS |
Contact Information
| Contractor | Moderno Pools Inc; Lic. No.: 862353-C53 | 23890 COOPER HILL DR SUITE #225 VALENCIA, CA 91354 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/22/2022 | No Access for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 9/23/2022 | Approved | DAVID FEILER |
| Pool Piping | 9/23/2022 | Approved | DAVID FEILER |
| Pre-Gunite | 9/23/2022 | Approved | DAVID FEILER |
| Rough-Electrical | 9/23/2022 | Approved | DAVID FEILER |
| Deputy Shotcrete | 9/29/2022 | No Access for Inspection | DAVID FEILER |
| Grounding or Bonding | 10/12/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Not Ready | DAVID FEILER |
| Gas Piping or Gas Test | 11/4/2022 | Corrections Issued | CLAYTON GRAHAM |
| Gas Piping or Gas Test | 11/8/2022 | Approved | ANDREW NAVE |
| Special/Order Compliance | 11/8/2022 | Approved | ANDREW NAVE |
| Enclosure/Fence | 11/16/2022 | Corrections Issued | DAVID FEILER |
| Enclosure/Fence | 11/18/2022 | Approved | DAVID FEILER |
| Special/Order Compliance | 11/18/2022 | Partial Inspection | DAVID FEILER |
| Pool Equipment Noise Test | 12/19/2022 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 1/6/2023 | Conditional Approval | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | EVAN COOPER |