1110 N BUNDY DR 90049
Certificate Information: 1110 N BUNDY DR 90049
- Application / Permit
- 22047-20000-01221
- Plan Check / Job No.
- B22VN09268
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL THE (E) POOL AND ADD (N) 5' X 12' IRR SHAPED SPA SPA, PER LA CIT STD PLAN No.268 AND ENG DETAILS # 551, #640
- Permit Issued
- Issued on 7/7/2022
- Issuing Office
- Current Status
- CofO Issued on 11/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/15/2022 | LUISANGEL VALENZUELA |
| Issued | 7/7/2022 | APPLICANT |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| CofO in Progress | 11/3/2023 | CARLOS MATAMOROS |
| Permit Finaled | 11/7/2023 | DANIEL ORRANTE |
| CofO Issued | 11/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/14/2022 | LUISANGEL VALENZUELA |
Contact Information
| Contractor | Lax Home Inc; Lic. No.: 1063552-B | 15021 VENTURA BLVD STE 810 SHERMAN OAKS, CA 91403 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 8/8/2022 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 8/8/2022 | Approved | JUAN VALENZUELA |
| Rough-Electrical | 8/8/2022 | Approved | JUAN VALENZUELA |
| Rough-Plumbing | 8/8/2022 | Approved | JUAN VALENZUELA |
| Deputy Other (see comments) | 8/9/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Deck | 2/7/2023 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 2/7/2023 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 4/12/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/24/2023 | No Access for Inspection | CARLOS MATAMOROS |
| Final | 8/24/2023 | No Access for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 8/24/2023 | No Access for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/11/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 9/11/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 9/11/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 9/18/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Final | 9/18/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Final | 11/2/2023 | OK to Issue CofO | CARLOS MATAMOROS |