3721 N ALOMAR DR 91423

Certificate Information: 3721 N ALOMAR DR 91423

Application / Permit
22047-20000-01107
Plan Check / Job No.
B22VN08335
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 37' 10" X 18' SWIMMING POOL WITH ATTACHED 8' X 8' SPA ON PILES. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 5/30/2025
Issuing Office
Valley
Current Status
Issued on 5/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/27/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 GURUNATH NESARAJAH
Corrections Issued 6/4/2022 GURUNATH NESARAJAH
Quality Review Completed 6/9/2022 OMID HEDAYAT
Building Plans Picked Up 6/10/2022 APPLICANT
Applicant returned to address corrections 10/7/2022 GURUNATH NESARAJAH
Plan Check Approved 5/30/2025 GURUNATH NESARAJAH
Issued 5/30/2025 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 5/19/2025 ALEX VELA
ZA Case Cleared 5/19/2025 ALEX VELA

Contact Information

Architect Lynch,, Todd Michael; Lic. No.: C35996 1068 YALE STREET      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1185 HERITAGE FARM RD      HICKORY, NC 28601
Engineer Djoneva,, Diana Ivanova; Lic. No.: C73805 3241 HENRIETTA AVE      LA CRESCENTA, CA 91214
Engineer Guh,, Tien-Jin Jeff; Lic. No.: S3218 705 SAN VICENTE BLVD      SANTA MONICA, CA 90402
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 24736 CALVERT STREET      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 12/9/2025 Conditional Approval JUAN VALENZUELA
Piling/Pier/Caisson 12/9/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Grading 12/10/2025 Conditional Approval JOAQUIN GREENOUGH
Deputy Grading 12/11/2025 Conditional Approval JUAN VALENZUELA
Piling/Pier/Caisson 12/16/2025 Corrections Issued CHRISTOPHE COCHRAN
Piling/Pier/Caisson 12/22/2025 Approved CHRISTOPHE COCHRAN
Deputy Other (see comments) 12/23/2025 Conditional Approval JUAN VALENZUELA
Gas Piping or Gas Test 3/16/2026 Approved CHRISTOPHE COCHRAN
Grounding or Bonding 3/16/2026 Partial Approval CHRISTOPHE COCHRAN
Gunite 3/16/2026 Approved CHRISTOPHE COCHRAN
Pool Piping 3/16/2026 Approved CHRISTOPHE COCHRAN
Pre-Gunite 3/16/2026 Approved CHRISTOPHE COCHRAN
Rough-Electrical 3/16/2026 Approved CHRISTOPHE COCHRAN
Rough-Plumbing 3/16/2026 Approved CHRISTOPHE COCHRAN
Deputy Shotcrete 3/17/2026 Conditional Approval RAUL OLAGI