6119 N SATSUMA AVE 91606
Certificate Information: 6119 N SATSUMA AVE 91606
- Application / Permit
- 22047-20000-01065
- Plan Check / Job No.
- B22VN08068
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15'-6" X 18' POOL AND 7' X 7' SPA PER STANDARD PLAN 268.
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | SERGIO MUNIZ |
| Corrections Issued | 5/25/2022 | SERGIO MUNIZ |
| Plan Check Approved | 6/3/2022 | SERGIO MUNIZ |
| Issued | 6/3/2022 | APPLICANT |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| CofO in Progress | 11/29/2022 | JOHN HAYES |
| CofO Issued | 2/4/2023 | MICHAEL SMITH |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/24/2022 | Corrections Issued | JOHN HAYES |
| Pre-Gunite | 7/5/2022 | Approved | JOHN HAYES |
| Deck | 8/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Enclosure/Fence | 9/27/2022 | Corrections Issued | JOHN HAYES |
| Enclosure/Fence | 10/11/2022 | Not Ready for Inspection | JOHN HAYES |
| Enclosure/Fence | 10/13/2022 | Approved | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 10/31/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/31/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Not Ready | JOHN HAYES |
| Equipment Noise Level | 11/9/2022 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 11/9/2022 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 11/18/2022 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 11/18/2022 | Approved | JENNIFER RABUCHIN |
| Final | 11/18/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | JENNIFER RABUCHIN |