20561 W WISTERIA CT 91326
Certificate Information: 20561 W WISTERIA CT 91326
- Application / Permit
- 22047-20000-01049
- Plan Check / Job No.
- B22VN07941
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 22' X 32' SWIMMING POOL WITH ATTACHED 8' X 8' SPA. WORK PER STANDARD PLAN #268 AND ENGINEER DETAILS.
- Permit Issued
- Issued on 6/8/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | ROSENDO MEDINA |
| Corrections Issued | 5/28/2022 | ROSENDO MEDINA |
| Plan Check Approved | 6/8/2022 | ROSENDO MEDINA |
| Issued | 6/8/2022 | APPLICANT |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| CofO in Progress | 10/19/2022 | DAVID SCANTLIN |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
| CofO Issued | 11/2/2022 | JOHN JANSON |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/30/2022 | ROSENDO MEDINA |
| "T" removal | Cleared | 6/7/2022 | DANG NGUYEN |
| Tract Map conditions | Cleared | 6/7/2022 | DANG NGUYEN |
| Tract Map conditions | Cleared | 6/7/2022 | DANG NGUYEN |
| Tract Map conditions | Cleared | 6/7/2022 | DANG NGUYEN |
| ZA Case | Cleared | 6/7/2022 | DANG NGUYEN |
| ZA Case | Cleared | 6/7/2022 | DANG NGUYEN |
Contact Information
| Contractor | All Outdoor G O Construction Inc; Lic. No.: 721947-C53 | 20130 PICCADILLY LANE PORTER RANCH, CA 91326 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/15/2022 | Approved | DAVID SCANTLIN |
| Deputy Shotcrete | 6/21/2022 | Conditional Approval | DAVID SCANTLIN |
| Deck | 7/22/2022 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 8/15/2022 | Approved | DAVID SCANTLIN |
| Pool Equipment Noise Test | 8/31/2022 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 9/1/2022 | Approved | DAVID SCANTLIN |
| Final | 9/1/2022 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Approved | DAVID SCANTLIN |
| Final | 10/19/2022 | OK to Issue CofO | DAVID SCANTLIN |