5030 N NEWCASTLE AVE 91316
Certificate Information: 5030 N NEWCASTLE AVE 91316
- Application / Permit
- 22047-20000-01004
- Plan Check / Job No.
- B22VN07580
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13' X 30' SWIMMING POOL AND 6'-6" X 6'-6" SPA WITHIN PER STANDARD PLAN #268
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 5/18/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Plan Check Approved | 8/10/2022 | JEROME MAGAT PALMA |
| Issued | 8/10/2022 | APPLICANT |
| CofO in Progress | 11/21/2022 | DAVID SANDOVAL |
| CofO Issued | 12/27/2022 | MICHAEL SMITH |
| Permit Finaled | 12/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/18/2022 | JEROME MAGAT PALMA |
| Construction near power lines | Cleared | 7/28/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/28/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/14/2022 | Approved | DAVID SANDOVAL |
| Deputy Shotcrete | 9/16/2022 | Conditional Approval | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Deck | 10/12/2022 | Approved | JUSTIN HAWLEY |
| Enclosure/Fence | 10/26/2022 | Approved | DAVID SANDOVAL |
| Equipment Noise Level | 11/9/2022 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Approved | DAVID SANDOVAL |
| Final | 11/17/2022 | Partial Approval | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | DAVID SANDOVAL |
| Final | 11/21/2022 | OK to Issue CofO | DAVID SANDOVAL |