14009 N CLAYWOOD AVE 91342
Certificate Information: 14009 N CLAYWOOD AVE 91342
- Application / Permit
- 22047-20000-00999
- Plan Check / Job No.
- B22VN07557
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL W/ SPA
- Permit Issued
- Issued on 5/19/2023
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2022 | RACHEL BEYENE |
| Corrections Issued | 7/19/2022 | RACHEL BEYENE |
| Plan Check Approved | 8/10/2022 | FERNANDO FLORES |
| Issued | 5/19/2023 | APPLICANT |
| CofO in Progress | 3/6/2025 | KEVIN BERBERYAN |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
| CofO Issued | 4/22/2025 | RUBEN SALAS |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/4/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 12/4/2023 | Corrections Issued | KEVIN BERBERYAN |
| Pre-Gunite | 12/4/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 2/22/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 2/22/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Pre-Gunite | 2/22/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Not Ready | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Partial Inspection | KEVIN BERBERYAN |
| Final | 1/28/2025 | Corrections Issued | KEVIN BERBERYAN |
| Pre-Gunite | 1/28/2025 | Partial Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 2/13/2025 | Approved | KEVIN BERBERYAN |
| Final | 2/13/2025 | Corrections Issued | KEVIN BERBERYAN |
| Pre-Gunite | 2/13/2025 | Conditional Approval | KEVIN BERBERYAN |
| Final | 3/6/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Pre-Gunite | 3/6/2025 | Approved | KEVIN BERBERYAN |