14009 N CLAYWOOD AVE 91342

Certificate Information: 14009 N CLAYWOOD AVE 91342

Application / Permit
22047-20000-00999
Plan Check / Job No.
B22VN07557
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL W/ SPA
Permit Issued
Issued on 5/19/2023
Issuing Office
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 7/19/2022 RACHEL BEYENE
Corrections Issued 7/19/2022 RACHEL BEYENE
Plan Check Approved 8/10/2022 FERNANDO FLORES
Issued 5/19/2023 APPLICANT
CofO in Progress 3/6/2025 KEVIN BERBERYAN
Permit Finaled 4/22/2025 RUBEN SALAS
CofO Issued 4/22/2025 RUBEN SALAS
Permit Finaled 4/22/2025 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/4/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 12/4/2023 Corrections Issued KEVIN BERBERYAN
Pre-Gunite 12/4/2023 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 2/22/2024 Corrections Issued CRAIG DAVIS
Final 2/22/2024 Not Ready for Inspection CRAIG DAVIS
Pre-Gunite 2/22/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Not Ready CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Not Ready KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 1/28/2025 Partial Inspection KEVIN BERBERYAN
Final 1/28/2025 Corrections Issued KEVIN BERBERYAN
Pre-Gunite 1/28/2025 Partial Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 2/13/2025 Approved KEVIN BERBERYAN
Final 2/13/2025 Corrections Issued KEVIN BERBERYAN
Pre-Gunite 2/13/2025 Conditional Approval KEVIN BERBERYAN
Final 3/6/2025 OK to Issue CofO KEVIN BERBERYAN
Pre-Gunite 3/6/2025 Approved KEVIN BERBERYAN