6218 N TOPEKA DR 91335

Certificate Information: 6218 N TOPEKA DR 91335

Application / Permit
22047-20000-00977
Plan Check / Job No.
B22VN07407
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL WITH SPLASH PAD AND SPA PER LA CITY STD PLAN No. 265 AND ENG DETAIL
Permit Issued
Issued on 10/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2022 APPLICANT
Assigned to Plan Check Engineer 5/17/2022 LUISANGEL VALENZUELA
Corrections Issued 5/18/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 7/13/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 7/19/2022 APPLICANT
Plan Check Approved 10/14/2022 MINA HABILI
Issued 10/14/2022 APPLICANT
CofO in Progress 3/10/2023 JON MCHUGH
CofO in Progress 3/15/2023 JON MCHUGH
Permit Finaled 3/20/2023 JOHN JANSON
CofO Issued 3/20/2023 JOHN JANSON
Permit Finaled 3/20/2023 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 9/24/2022 RIDWAN HARDY
Construction within easement Cleared 9/24/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/31/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/14/2022 Corrections Issued SEAN HAUPT
Rough-Plumbing 11/14/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/18/2022 Approved SEAN HAUPT
Pre-Gunite 11/18/2022 Approved SEAN HAUPT
Rough-Plumbing 11/18/2022 Approved SEAN HAUPT
Special/Order Compliance 11/18/2022 Partial Inspection KRISTEN CAUSEY
Deputy Shotcrete 11/22/2022 Conditional Approval KRISTEN CAUSEY
Enclosure/Fence 2/14/2023 Approved SEAN HAUPT
Grounding or Bonding 2/14/2023 Approved SEAN HAUPT
Equipment Noise Level 2/23/2023 Approved FELIPE PENICHE
Final 2/27/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved JON MCHUGH
Final 3/1/2023 Partial Approval JON MCHUGH
Final 3/15/2023 OK to Issue CofO JON MCHUGH