3178 N ABINGTON DR 90210

Certificate Information: 3178 N ABINGTON DR 90210

Application / Permit
22047-20000-00930
Plan Check / Job No.
B22VN07054
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 36'-8" X 14' SWIMMING POOL AND 6' X 6' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAILS
Permit Issued
Issued on 6/8/2022
Issuing Office
Current Status
CofO Issued on 6/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2022 APPLICANT
Assigned to Plan Check Engineer 5/13/2022 JEROME MAGAT PALMA
Corrections Issued 5/14/2022 JEROME MAGAT PALMA
Plan Check Approved 6/3/2022 JEROME MAGAT PALMA
Issued 6/8/2022 APPLICANT
Building Plans Picked Up 6/10/2022 APPLICANT
CofO in Progress 5/26/2023 MICHAEL PELHAM
Permit Finaled 6/5/2023 DANIEL ORRANTE
CofO Issued 6/5/2023 DANIEL ORRANTE
Permit Finaled 6/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/15/2022 JEROME MAGAT PALMA
Specific Plan Cleared 5/23/2022 PABLO ESTRADA
ZA Case Cleared 5/23/2022 PABLO ESTRADA
ZA Case Cleared 5/23/2022 PABLO ESTRADA

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Proofing Certificate 12/15/2022 Approved GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 12/15/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 12/15/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 12/16/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 2/28/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 4/27/2023 Corrections Issued MICHAEL PELHAM
Enclosure/Fence 5/2/2023 Conditional Approval MICHAEL PELHAM
Final 5/2/2023 Corrections Issued MICHAEL PELHAM
Pool Equipment Noise Test 5/16/2023 Approved ZEYDI STEWART
Excavation/Setback/Form/Re-Bar 5/18/2023 Approved CARLOS MATAMOROS
Final 5/18/2023 Corrections Issued CARLOS MATAMOROS
Pre-Gunite 5/18/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Not Ready CARLOS MATAMOROS
Final 5/23/2023 Corrections Issued MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Not Ready MICHAEL PELHAM
Final 5/26/2023 OK to Issue CofO MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Approved MICHAEL PELHAM