23501 W BERDON ST 91367

Certificate Information: 23501 W BERDON ST 91367

Application / Permit
22047-20000-00870
Plan Check / Job No.
B22VN06679
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16'-0" x 36'-0" POOL WITH A 9'-0 x 9'-0" SPA PER STD. CITY PLAN # 268
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 4/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/2/2022 ALFRED RAMIREZ
Corrections Issued 5/2/2022 ALFRED RAMIREZ
Issued 6/14/2022 APPLICANT
Building Plans Picked Up 6/23/2022 APPLICANT
CofO in Progress 10/20/2025 TROY SANDERS
Permit Finaled 4/11/2026 MICHAEL PELHAM
CofO Issued 4/11/2026 MICHAEL PELHAM
Permit Finaled 4/11/2026 MICHAEL PELHAM

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/2/2022 ALFRED RAMIREZ
Construction near power lines Cleared 6/1/2022 RIDWAN HARDY
Construction within easement Cleared 6/1/2022 RIDWAN HARDY

Contact Information

Contractor Elite Remodeling & Development Inc; Lic. No.: 975264-B 8949 RESEDA BLVD STE #217      NORTHRIDGE, CA 91324
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 6/30/2022 Partial Approval TROY SANDERS
Rough-Electrical 6/30/2022 Partial Approval TROY SANDERS
Pre-Gunite 4/15/2025 No Access for Inspection GEVORK IPCHYAN
Rough-Electrical 4/15/2025 No Access for Inspection GEVORK IPCHYAN
Rough-Plumbing 4/15/2025 No Access for Inspection GEVORK IPCHYAN
Pre-Gunite 4/22/2025 Approved TROY SANDERS
Deputy Shotcrete 4/24/2025 Conditional Approval TROY SANDERS
Pool/Spa Cover 6/2/2025 Not Ready for Inspection TROY SANDERS
Enclosure/Fence 8/4/2025 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 8/4/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Approved TROY SANDERS
Final 8/26/2025 Not Ready for Inspection TROY SANDERS
Final 9/5/2025 No Access for Inspection GEVORK IPCHYAN
Final 9/9/2025 Not Ready for Inspection TROY SANDERS
Final 9/19/2025 Not Ready for Inspection TROY SANDERS
Final 10/20/2025 OK to Issue CofO TROY SANDERS