22215 W MAYALL ST 91311
Certificate Information: 22215 W MAYALL ST 91311
- Application / Permit
- 22047-20000-00857
- Plan Check / Job No.
- B22VN06584
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 32' POOL WITH A 8' X 8' SPA PER LA CITY STANDARD PLAN #270
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- Issued on 5/18/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2022 | SEAN SHAHMIRI |
| Corrections Issued | 4/29/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 5/18/2022 | SEAN SHAHMIRI |
| Issued | 5/18/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Green Paradise Creation Inc; Lic. No.: 1017683-B | 17933 TOPHAM ST ENCINO, CA 91316 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/26/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Pre-Gunite | 7/29/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pre-Gunite | 8/3/2022 | Approved | CHRIS CHRISTENSEN |
| Rough-Mechanical | 8/3/2022 | Approved | CHRIS CHRISTENSEN |
| Deputy Shotcrete | 8/4/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Deck | 10/19/2022 | Approved | JUSTIN HAWLEY |
| Enclosure/Fence | 5/24/2023 | Corrections Issued | JOHN KIDWELL |
| Equipment Noise Level | 11/14/2023 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 11/14/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 12/5/2023 | Approved | JEFFREY HARTLINE |
| Final | 12/5/2023 | Partial Approval | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | JEFFREY HARTLINE |