3944 W EDENHURST AVE 90039
Certificate Information: 3944 W EDENHURST AVE 90039
- Application / Permit
- 22047-20000-00840
- Plan Check / Job No.
- B22VN06416
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12'x20' POOL AND SPA PER LA CITY STANDARD PLANS #268
- Permit Issued
- Issued on 6/20/2022
- Issuing Office
- Current Status
- CofO Issued on 8/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | SEAN SHAHMIRI |
| Corrections Issued | 5/26/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 5/26/2022 | SEAN SHAHMIRI |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| Issued | 6/20/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/31/2023 | RONALD MYRICK |
| CofO Issued | 8/31/2023 | RONALD MYRICK |
| Permit Finaled | 8/31/2023 | RONALD MYRICK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Hansen Pool Construction Inc; Lic. No.: 991006-C53 | 13046 CHEJU CIRCLE EASTVALE, CA 92880 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Approved | HAMIK HARTOUNIAN |
| Gas Piping or Gas Test | 1/23/2023 | Approved | HAMIK HARTOUNIAN |
| Pre-Gunite | 1/23/2023 | Approved | HAMIK HARTOUNIAN |
| Rough-Electrical | 1/23/2023 | Approved | HAMIK HARTOUNIAN |
| Rough-Plumbing | 1/23/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Shotcrete | 1/24/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Grounding or Bonding | 1/31/2023 | Approved | HAMIK HARTOUNIAN |
| Enclosure/Fence | 5/23/2023 | Corrections Issued | JEFFREY MEAD |
| Enclosure/Fence | 6/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Enclosure/Fence | 6/28/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Enclosure/Fence | 7/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Enclosure/Fence | 7/10/2023 | Approved | ALIZAH MAYAGOITIA |
| Equipment Noise Level | 7/25/2023 | Approved | ZEYDI STEWART |
| ELECTRICAL-Final | 7/27/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 7/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 7/27/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 8/24/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Approved | HAMIK HARTOUNIAN |