17711 W CORINTHIAN DR 91316
Certificate Information: 17711 W CORINTHIAN DR 91316
- Application / Permit
- 22047-20000-00781
- Plan Check / Job No.
- B22VN05846
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 31' X 18' POOL AND 10' X 10' SPA PER STANDARD PLAN 268 & ENG. DETAILS #501, 551
- Permit Issued
- Issued on 7/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | SERGIO MUNIZ |
| Corrections Issued | 4/23/2022 | SERGIO MUNIZ |
| Plan Check Approved | 6/24/2022 | SERGIO MUNIZ |
| Issued | 7/3/2022 | APPLICANT |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| CofO in Progress | 12/21/2023 | SEAN HAUPT |
| CofO Issued | 1/8/2024 | JOHN JANSON |
| Permit Finaled | 1/8/2024 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deck | 11/29/2022 | Corrections Issued | DAVID SANDOVAL |
| Gas Piping or Gas Test | 11/29/2022 | Approved | DAVID SANDOVAL |
| Pre-Gunite | 11/29/2022 | Approved | DAVID SANDOVAL |
| Rough-Electrical | 11/29/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Shotcrete | 11/30/2022 | Conditional Approval | DAVID SANDOVAL |
| Grounding or Bonding | 8/22/2023 | Approved | SEAN HAUPT |
| Enclosure/Fence | 12/4/2023 | Corrections Issued | DAVID SCANTLIN |
| Enclosure/Fence | 12/6/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 12/14/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 12/14/2023 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Not Ready | JOHN KIDWELL |
| Equipment Noise Level | 12/19/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 12/20/2023 | Approved | SEAN HAUPT |
| Final | 12/20/2023 | OK to Issue CofO | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | SEAN HAUPT |