933 N ENCHANTED WAY 90272
Certificate Information: 933 N ENCHANTED WAY 90272
- Application / Permit
- 22047-20000-00702
- Plan Check / Job No.
- B22VN05268
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL THE (E) POOL AND ADD A NEW SPA PER STANDARD CITY PLAN #268, ADD SPILL OVER AND 18" DEPTH WADING POOL.
- Permit Issued
- Issued on 10/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2022 | ALFRED RAMIREZ |
| Corrections Issued | 4/11/2022 | ALFRED RAMIREZ |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Plan Check Approved | 8/11/2022 | MINA HABILI |
| Issued | 10/5/2022 | APPLICANT |
| CofO in Progress | 5/24/2024 | EVAN COOPER |
| Permit Finaled | 6/28/2024 | DANIEL ORRANTE |
| CofO Issued | 6/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/11/2022 | VASIL MIHALEV |
| Coastal Zone | Cleared | 8/9/2022 | MAYELA VILLA |
| ZI | Cleared | 8/9/2022 | MAYELA VILLA |
Contact Information
| Contractor | Gutierrez Jr Everardo; Lic. No.: 1039460-C53 | 16120 RINALDI STREET GRANADA HILLS, CA 91344 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/6/2022 | Conditional Approval | BRENDAN LOONEY |
| Pre-Gunite | 10/12/2022 | Corrections Issued | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 2/7/2023 | Approved | BRENDAN LOONEY |
| Pool Piping | 2/7/2023 | Approved | BRENDAN LOONEY |
| Pre-Gunite | 2/7/2023 | Approved | BRENDAN LOONEY |
| Enclosure/Fence | 7/6/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 7/6/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 7/12/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deck | 4/4/2024 | Approved | EVAN COOPER |
| Grounding or Bonding | 4/4/2024 | Approved | EVAN COOPER |
| Pool/Spa Cover | 4/4/2024 | Corrections Issued | EVAN COOPER |
| Pool Equipment Noise Test | 4/9/2024 | Approved | EUSEBIO GUZMAN |
| ELECTRICAL-Final | 5/24/2024 | Approved | EVAN COOPER |
| Final | 5/24/2024 | OK to Issue CofO | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Approved | EVAN COOPER |