7621 S STETSON AVE 90045
Certificate Information: 7621 S STETSON AVE 90045
- Application / Permit
- 22047-20000-00681
- Plan Check / Job No.
- B22VN05004
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 12' X 21'- 8" SWIMMING POOL PER LACITY STANDARD PLAN #268 AND SUPPLMENTAL DETAILS PER ENGINEERING.
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2022 | OMAR GARNICA |
| Plan Check Approved | 4/13/2022 | OMAR GARNICA |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 9/29/2022 | HERBERT GIRON |
| CofO in Progress | 9/29/2022 | HERBERT GIRON |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/24/2022 | Approved | DAVID FEILER |
| Deputy Shotcrete | 6/27/2022 | Conditional Approval | HERBERT GIRON |
| Deck | 7/22/2022 | Approved | CLAYTON GRAHAM |
| Gas Piping or Gas Test | 7/22/2022 | Approved | CLAYTON GRAHAM |
| Enclosure/Fence | 8/19/2022 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 8/24/2022 | Approved | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Approved | BOBBY KEY |
| Final | 9/7/2022 | Corrections Issued | BOBBY KEY |
| Pool Equipment Noise Test | 9/7/2022 | Approved | JAMES VORHIS |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Not Ready | BOBBY KEY |
| Final | 9/14/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Not Ready | HERBERT GIRON |
| Final | 9/28/2022 | OK to Issue CofO | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | HERBERT GIRON |