4730 N CONCHITA WAY 91356

Certificate Information: 4730 N CONCHITA WAY 91356

Application / Permit
22047-20000-00671
Plan Check / Job No.
B22VN04951
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 36' X 17' POOL WITH 7'-10" X 7' SPA ON PILES ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/3/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/6/2022 OMID HEDAYAT
Building Plans Picked Up 5/11/2022 APPLICANT
Applicant returned to address corrections 8/1/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/5/2022 SEWADA ZADOORAN MILAGARDI
Issued 10/26/2022 APPLICANT
CofO in Progress 10/25/2023 SEAN HAUPT
CofO Issued 11/30/2023 JOHN JANSON
Permit Finaled 11/30/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/5/2022 ROBERT HUGHES

Contact Information

Contractor Ortam Construction Inc; Lic. No.: 880225-B 4500 PARK GRANADA #202      CALABASAS, CA 91302
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/27/2023 Not Ready for Inspection SEAN HAUPT
Pre-Inspection 7/20/2023 Partial Approval JOHN KIDWELL
Deputy Shotcrete 7/26/2023 Approved SEAN HAUPT
Piling/Pier/Caisson 7/27/2023 Partial Approval SEAN HAUPT
Deputy Other (see comments) 7/28/2023 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 8/9/2023 Partial Approval SEAN HAUPT
Deputy Other (see comments) 8/16/2023 Approved SEAN HAUPT
Pre-Gunite 8/24/2023 Approved SEAN HAUPT
Rough-Electrical 8/24/2023 Approved SEAN HAUPT
Rough-Plumbing 8/24/2023 Approved SEAN HAUPT
Deputy Shotcrete 8/28/2023 Partial Approval JOHN KIDWELL
Enclosure/Fence 10/10/2023 Approved SEAN HAUPT
Grounding or Bonding 10/10/2023 Approved SEAN HAUPT
Equipment Noise Level 10/17/2023 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 10/18/2023 Approved SEAN HAUPT
Final 10/18/2023 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Approved SEAN HAUPT
Final 10/24/2023 OK to Issue CofO SEAN HAUPT
Enclosure/Fence 11/14/2023 Corrections Issued SEAN HAUPT
Enclosure/Fence 11/30/2023 Approved SEAN HAUPT