11809 W ALLASEBA DR 90066
Certificate Information: 11809 W ALLASEBA DR 90066
- Application / Permit
- 22047-20000-00616
- Plan Check / Job No.
- B22VN04587
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 26' X 14' SWIMMING POOL AND 9' X 9' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 3/29/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 6/9/2022 | JEROME MAGAT PALMA |
| Issued | 6/10/2022 | APPLICANT |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| CofO in Progress | 4/26/2023 | HERBERT GIRON |
| Permit Finaled | 5/2/2023 | DANIEL ORRANTE |
| CofO Issued | 5/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/29/2022 | JEROME MAGAT PALMA |
| Construction near power lines | Cleared | 6/4/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/4/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Coastal Aquatic Creations; Lic. No.: 697943-C53 | 11730 GATEWAY BLVD LOS ANGELES, CA 90064 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/24/2022 | Approved | KENNETH NAGLE |
| Gas Piping or Gas Test | 10/24/2022 | Approved | KENNETH NAGLE |
| Pool Piping | 10/24/2022 | Approved | KENNETH NAGLE |
| Pre-Gunite | 10/24/2022 | Approved | KENNETH NAGLE |
| Rough-Electrical | 10/24/2022 | Approved | KENNETH NAGLE |
| Rough-Plumbing | 10/24/2022 | Approved | KENNETH NAGLE |
| Deputy Shotcrete | 10/26/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deck | 1/18/2023 | Approved | JOHNNY MIRANDA |
| Deck | 3/10/2023 | Approved | JEREMY TODD |
| Enclosure/Fence | 3/21/2023 | Approved | JOHNNY MIRANDA |
| Pool Equipment Noise Test | 4/13/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 4/21/2023 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/26/2023 | Approved | HERBERT GIRON |
| Final | 4/26/2023 | OK to Issue CofO | HERBERT GIRON |