3039 S DANNYHILL DR 90064

Certificate Information: 3039 S DANNYHILL DR 90064

Application / Permit
22047-20000-00598
Plan Check / Job No.
B22VN04487
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 11' X 58'2" POOL WITH 11' X 8' SPA PER STD PLAN # 268.
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
CofO Issued on 1/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 PINANK PATEL
Corrections Issued 3/24/2022 PINANK PATEL
Plan Check Approved 6/20/2022 PINANK PATEL
Issued 6/21/2022 APPLICANT
Building Plans Picked Up 6/23/2022 APPLICANT
CofO in Progress 1/2/2024 OGANES TARAKHCHYAN
Permit Finaled 1/5/2024 DANIEL ORRANTE
CofO Issued 1/5/2024 DANIEL ORRANTE
Permit Finaled 1/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/24/2022 PINANK PATEL
Specific Plan Cleared 4/1/2022 PABLO ESTRADA
ZI Cleared 4/1/2022 PABLO ESTRADA
Construction near power lines Cleared 6/3/2022 RIDWAN HARDY
Construction within easement Cleared 6/3/2022 RIDWAN HARDY

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gunite 12/22/2022 Approved OGANES TARAKHCHYAN
Pre-Inspection 2/1/2023 Corrections Issued ASHLEY THOMPSON
Pre-Gunite 2/6/2023 Approved ASHLEY THOMPSON
Deputy Shotcrete 2/10/2023 Conditional Approval ASHLEY THOMPSON
Grounding or Bonding 4/6/2023 Approved ASHLEY THOMPSON
Enclosure/Fence 10/31/2023 Approved KENNETH NAGLE
Grounding or Bonding 11/16/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Pool Equipment Noise Test 11/16/2023 Approved ANDEY CHAPARRO
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Final 11/21/2023 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 12/4/2023 Approved OGANES TARAKHCHYAN
Final 12/4/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Final 12/21/2023 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Not Ready JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Final 12/29/2023 Partial Approval OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/29/2023 SGSOV Approved OGANES TARAKHCHYAN